If your solar production meter is replaced at any time, the Massachusetts Production Tracking Service (PTS) will need the following information to ensure you do not miss out on additional production reporting windows:
- PTS ID
- The make and model of the new meter
- Last reading on the old meter (taken on the date of the swap)
- Meter swap date
- Initial meter reading on the new meter (taken on the date of the swap)
- The new meter's end of month reading (if the meter swap was outside of the 10-day reporting window)
The PTS administrators can be reached at pts@masscec.com